Washcoater & Coolant Filter Civil Works

Design & Engineering of Foundations & Washer Tank AutoCAD 2d layouts of foundations Inventor 3d modelling of foundations & stainless steel fabricated Washer tank Washcoater Tank – Installation of 316 stainless steel pre-fabricated tank Factory floor excavated for two sump pits, Washcoater foundation and drainage trenches ECL designed and fabricated 316 stainless steel Washer sump…

4 x Palletiser Removal

Mark up & match mark all Palletiser sections & parts, dismantle each Palletiser individually with Strappers & Pallet Conveying, remove the parts out of the factory and load into trucks for transport to new individual factories for each machine to be installed.

Palletiser Installation x 6

Offload & ingress the machine sections into the factory, raise the upper section and install the leg extensions for each Palletiser, move into position onto the datum lines for final assembly and installation using the Manitou type small crane.

Pipework Installations

Turnkey installation of equipment & pipework. Design, Engineering & Layouts of production line pipework. Full production line equipment pipework installation from main headers to machines. Photo’s for jobs include:- Cupping Press cooling water pipework in mild steel screwed pipe. Bodymaker HP & LP air, vacuum, coolant & cooling water in 316 stainless steel crimped pipe.…

Turnkey VMI Can Washer Installation – UK

This project was a complete bespoke turnkey package tailored to our clients individual requirements. Evans Canlines Ltd provided complete civil, mechanical & electrical Installation of two VMI can washers within a running production facility. All protective measures were strictly controlled and adhered to, in order to prevent contamination and maintain production throughout installation works.